1244.01

GENERAL PROCEDURE.

​(a) Subdivisions. Before any land is subdivided, the owner of the property to be subdivided, or his authorized agent, shall apply for and secure approval of the proposed subdivision in accordance with the following procedures, which include two (2) principal steps for a minor subdivision and five (5) principal steps for a major subdivision.

​(1) Minor Subdivision:

A. Concept Plan.

B. Record Plan.

​(2) Major Subdivision:

A. Pre-application Conference.

B. Concept Plan.

C. Preliminary Subdivision Plan.

D. Construction Drawings.

E. Record Plan

Table 1.

Summary of Subdivision Application Process, Major Subdivisions, City of Springboro Step Agency Module

Pre-Application Conference

for major subdivision

Director of Planning

1244.03(a)

Concept Plan Application

Director of Planning

1244.03(b)

Concept Plan Action / Approval

Director of Planning

1244.03(b)

Preliminary Plan Application

Director of Planning

1244.04

Preliminary Plan Action

Planning Commission

1244.04(b)

Construction Plans Submitted

for Review

City Engineer

1244.06

Record Plan Application

Director of Planning

1244.07(a)

Record Plan Action

Planning Commission and City Council

1244.07(a)

Performance and maintenance

bonds submitted

Director of Planning

1246.01

Record Plan Signatures

City Engineer, Mayor and Clerk of Council for major subdivisions;

Director of Planning for minor subdivisions

1244.10

Acceptance of Public Improvements

City Council

1246.03

​(b) Official Submission Dates. For the purpose of these regulations, for both major and minor subdivisions, the date of the meeting of the Planning Commission at which the public meeting or hearing on approval of a concept, preliminary or final subdivision plat, including any adjourned date thereof, is closed, shall constitute the Official Submission Date, of the plat on which the statutory period required for formal approval, conditional approval or disapproval of the concept, preliminary or record plan shall commence to run.

(Ord. 04-41. Passed 8-19-04.)